Church Road, Cherry Hill (CR 616)
- Awarded – April 21, 2022
- Partial NTP – November 14, 2022
Amended NTP – February 7, 2023
- 2nd Amended NTP – March 27, 2023
- Substantial Completion – December 1, 2023
- Final Completion – December 31, 2023
- Initial Award – $4,200,000